S.M.A.R.T. Project Planning Framework

Participation & Co-DeterminationPlanning & Evaluation

Basic Information

Age

14–26 years (independent project planning; within the range 12–26)

Group size

Project team of 3–8 young people

Duration

multi-phase process over several weeks to months, including follow-up support

Setting

analog/hybrid; accompanied process with regular meetings

Location

indoor,outdoor

Objectives

Translate vague wishes into verifiable goals – for mobile and digital offerings as well as for a youth project · plan your own project in a structured way from idea to evaluation · practice and pass on goal-setting as a team · strengthen self-efficacy and project competence

Procedure

Preparation

Clarify the framework before the appointment: time budget, money budget, and who will accompany the process. Print out the project framework or create it as a shared document, one copy per person. Provide a pinboard or flipchart for milestones. Bring a completed example goal that clearly shows the five criteria. Schedule follow-up appointments immediately – without follow-up, the framework remains just a sheet of paper.

Steps

1. Clarify the framework before anyone writes a goal: How much time, how much money, who accompanies? A goal that fails due to budget was never a goal.
2. Collect and say ideas out loud. Usually, there is a wish at the beginning, not a goal – “we want to reach more girls,” “our Discord should run.” This is the raw material.
3. Translate the wish into a S.M.A.R.T. goal. Five questions, in this order:
S – Specific: What exactly, for whom, at which location? “More girls” is not enough.
M – Measurable: How do you know it happened? Name the number and the source from which you read it.
A – Attractive and accepted: Does the team really want this, or is it just in the concept?
R – Realistic: Is it feasible with your people, your technology, your calendar?
T – Time-bound: By when? Without a date, everything shifts to later.
Mobile example: from “reach more girls” to “By December 15, at least five girls aged 12 to 16 attend three out of four pop-up meetings at the sports field – counted via the contact note in the Journal de Bord.” (→ P-05)
Digital example: from “our Discord should run” to “By the end of February, at least eight different young people write in #questions-to-the-team, and every question receives an answer within 24 hours.” (→ T-01)
4. Record non-goals. One sentence is enough: What will you consciously NOT do during this period? This protects against spreading yourself too thin and makes saying no easier later.
5. Distribute tasks and milestones, visible on a pinboard or board. Each task has a name and a date.
6. Set checkpoints – in a process over weeks, at least every two to three weeks take a quick look: Is it running, are there problems, does the goal need adjustment? An adjusted goal is not a failure; a silently abandoned one is.
7. Completion and follow-up: Compare goal with result, name deviations, take along what supports.

For familiarization: Go through step 3 together once with a real offer, thinking aloud. Then each person writes a goal alone and presents it to the team – the team only checks the five letters, not the idea. Whoever has written three goals this way no longer needs the framework on the table.

Materials

**Project framework as a template** (print or digital version with fields for the five phases and the S.M.A.R.T. criteria); writing materials or shared document; documentation option (folder/cloud); pinboard/flipchart for milestone and task overview; if applicable, budget overview/table

Why this method?

Why this method?

The framework fits in two ways. First, when a project team of 3–8 young people wants to implement their own project over weeks in a binding way. Second, within the team itself: when goals for a mobile or digital offering are set and when goal-setting is to be practiced. It is not suitable for spontaneous individual actions or without reliable accompaniment over distance.

Group dynamics

Unlike a single method, this process requires a committed core team of 3–8 young people who stay together over weeks and reliably take on tasks. Enough trust is needed to openly negotiate roles and honestly name deviations from the plan. A completely new group rarely manages this – the willingness for shared responsibility must already be present.

Reflection

Reflection questions

Are our goals really S.M.A.R.T. – especially: how do we measure? · Which “non-goals” do we avoid? · Where did implementation deviate from the plan, and why? · Would someone from outside understand the same goal immediately? · What do we take with us for the next project?

Pedagogical background

The framework makes an abstract project process tangible by breaking it down into five phases from idea to follow-up. The S.M.A.R.T. criteria force vague wishes to be translated into verifiable goals, and setting “non-goals” protects against spreading oneself too thin. By managing their own project, young people experience self-efficacy and build project competence.

Facilitation skills

The professional must moderate a multi-week to multi-month process without taking it over – they maintain the framework without prescribing content. They clarify the framework in advance regarding budget, timeframe, and support, and translate vague ideas with the group into S.M.A.R.T. goals. Perseverance is required to accompany the group through dry spells during implementation.

Risks

Critical points & sensitivities

The greatest risk is that the group loses motivation during the long implementation phase or that the project fails due to the real framework – therefore, clarify budget and feasibility honestly in advance. The goals must really come from the group; otherwise, the framework becomes a mere formality. The format requires independent planning and is suitable only from about 14 years old; younger participants need significantly more support.

Evaluation

How to recognize success

Commitment is measured, not individual activity: The process is successful if the team goes through all five phases up to the final report and largely achieves the formulated S.M.A.R.T. goals. A strong sign is that the group itself names in the follow-up what it takes with it for the next project. If the project fizzles out during implementation or the goals remain vague and unmeasurable, it has failed.